Chadwick Engineering has extensive experience in the metals industry with the majority of our projects in finishing, rolling and casting.  Our projects include the design of custom equipment and processes as well as the design of many retrofits and upgrades to existing equipment. 

Also, we have utilized our project management services on numerous metals industry projects.  The largest project we managed was a finishing plant expansion worth in excess of $60M. 

In the last ten years, we have also specialized in mechanical and electrical installation engineering.  In these projects, we close the gap between the new equipment supplier and our customer by providing all civil, mechanical and electrical details required to install and integrate the new equipment into the facility (see our Installation Engineering page for additional information).  Typically, our customers choose to compliment these services by having us support the project management as well.  This allows our customers the time to focus on the key details of the project.


Below please find a list of our major metals industry projects:

Major Finishing Projects:

  • Plate Stretcher Upgrade Project - 2009 – Installation Engineering & Project Management
  • Continuous Annealing Line – Water Quench System Upgrade – 2008 – 2009 – Equipment Design, Equipment Supply, Installation Engineering & Project Management
  • Tension Leveling Line Bowed Rolls - 2007 – 2008 – Equipment Design, Equipment Supply, Installation Engineering & Project Management
  • Continuous Annealing Line - Rewind Reheat Furnace - 2007 – 2008 – Installation Engineering & Project Management
  • Continuous Annealing Line - Rewind Oiler - 2007 – 2008 – Equipment Design and Equipment Supply
  • Tension Leveling Line – Entry Equipment Reconfiguration - 2006 – 2007 – Equipment Design, Equipment Supply, Installation Engineering & Project Management
  • Tension Leveling Line – Alkaline Cleaning System - 2005 – 2006 – Equipment Design, Installation Engineering & Project Management
  • COIL SEAL Steel Coil Packaging System – 2004 - 2005 – Equipment Design, Equipment Supply, Installation Engineering & Project Management
  • New Tension Leveling Line - 2004 – 2005 – Equipment Design, Installation Engineering & Project Management
  • Slit Coil Separating & Unitizing Line - 2003 – 2004 – Equipment Design, Equipment Supply, Installation Engineering & Project Management
  • COIL SEAL Upgrade to Aluminum Coil Packing Line – 2002 - 2003 – Equipment Design, Equipment Supply, Installation Engineering & Project Management
  • Continuous Annealing Line – Entry Equipment Upgrade - 2001 – 2002 – Equipment Design, Equipment Supply, Installation Engineering & Project Management
  • Heavy Gauge Slitting Line – Aluminum Strip Solvent Cleaning System - 2001 – 2002 – Equipment Design, Equipment Supply, Installation Engineering & Project Management
  • Plant Finishing Line Upgrade - 1999 – 2001 – Equipment Design, Equipment Supply, Installation Engineering & Project Management
  • Light Gauge Tension Leveling Line – Aluminum Strip Solvent Cleaning System - 1998 – 1999 – Equipment Design, Equipment Supply, Installation Engineering & Project Management
  • Packaging Line – Coil OD Banding System – 1998 – 1999 – Equipment Design and Equipment Supply
  • Light Gauge Slitting Line – Aluminum Strip Solvent Cleaning System - 1997 – 1998 – Equipment Design, Equipment Supply, Installation Engineering & Project Management
  • Heavy Gauge Tension Leveling Line – Aluminum Strip Solvent Cleaning System - 1995 – 1996 – Equipment Design, Equipment Supply, Installation Engineering & Project Management
  • Tension Leveling Line – Pull Bridle Redesign - 1995 – 1996 – Equipment Design and Installation Engineering
  • Coil Packaging Line - 1990 – 1992 – Equipment Design and Installation Engineering

Major Rolling Projects:

  • Hot Mill - Profile Gauge Replacement – 2008 – 2009 – Installation Engineering & Project Management
  • Hot Mill – Coil OD Banding System – 2006 – 2007 – Equipment Design and Equipment Supply
  • Cold Mill – Coloring Roll Retrofit – 2006 – 2007 – Installation Engineering & Project Management
  • Hot Mill - Profile Gauge Replacement – 2005 – 2007– Installation Engineering & Project Management
  • Cold Mill – Coil Conveyor Redesign & Replacement - 2004 – 2006 – Installation Engineering & Project Management
  • Hot Mill Side Trimmer – 2002 – 2003 – Installation Engineering & Project Management
  • Hot Mill – Exit End Coolant Blowoff – 2005 – 2007 – Equipment Design
  • Hot Mill – Coil OD / ID Banding System – 2006 – 2007 – Equipment Design and Equipment Supply

Major Casting Projects:

  • Upgrade of Melting Furnace from Recuperative to Regenerative Burners – 2008 to 2009 – Installation Engineering
  • Upgrade of Sow Drying Furnace from Recuperative to Regenerative Burners – 2008 to 2009 – Installation Engineering
  • Ingot Stacking and Strapping System – 2008 – Equipment Design, Equipment Supply, Installation Engineering & Project Management
  • New DC Casting Pit – 2004 – 2005 – Installation Engineering & Project Management
  • High Speed Aluminum Belt Caster Refurbishment - 2004 – 2005 – Equipment Design
  • Proprietary High Speed Aluminum Belt Caster – 2002 – 2004 – Equipment Design, Equipment Supply, Installation Engineering & Project Management
  • Ingot Stacking and Strapping System – 2001 - 2002 – Equipment Design, Equipment Supply, Installation Engineering & Project Management
     